Location: Arundel, QLD , 4214
Project Information
Our second project this week took us locally to Arundel in the Gold Coast to complete a structural steel installation for a mezzanine floor extension. Engineered to expand the client’s overhead footprint, the project delivered the core structural framework ahead of the client’s planned interior fit-out.
Project Overview & Engineering Specs
- Scope: Supply and installation of mezzanine structural steelwork only (22 m² addition).
- Load Rating: Engineered to a uniform distributed load capacity of 3 kPa, designed specifically for secondary floor loading and future storage use.
- Compliance Certification: Complete structural engineering design and provision of a Queensland Form 15 Compliance Certificate for Building Design covering the new structural framework.
Site Logistics & Installation Following a 4 week fabrication window from order placement, our crew was on-site in Arundel for installation.
Utilizing two scissor lifts concurrently, the team systematically hoisted, positioned, and bolted the structural steel columns and bearer/joist framing into place. The entire structural assembly was completed in just half a day, securing a solid, certified foundation for the client’s upcoming flooring installation & fir out, while keeping warehouse disruption to an absolute minimum.